New Parking Signage to be Installed Beginning Today in Downtown Cortland – Milling Begins Wednesday
Work continues along for the reconstruction of Main Street in Downtown Cortland. Beginning today, Crown City Rising says new signage will be installed. Signage will include guidance on the new reverse angle parking.
Also wrapping up work, with an anticipated completion of June 20th, is the work on the pocket park, rain gardens, and decorative brick pavers along Main Street. Crews are also continuing their work repairing sidewalks that the city has deemed unsatisfactory.
The intersection of Main Street and Clinton and Groton Ave. is also scheduled to be milled this Wednesday, June 18th. Crown City Rising says the milling processing of the intersection may result in a temporary full-day closure of the intersection. Delays are expected with detour signage in place. The milling is needed as crews prepare Main Street for final paving.
Updates may be found at CrownCityRising.com.