Homer Town Board Approves Stormwater Management Plan & Road Maintenance Plan For Scott Road Solar Project
The Homer Town Board unanimously approved two resolutions related to the Scott Road Solar Project. One related to the stormwater management plan and another for a road maintenance plan during the construction phase of the project. The project itself will be located at 331 Houghton Hill Road in the Town of Homer.
Town Attorney Dan Ellis provided an overview of the two agreements for the town board to vote on for acceptance and Supervisor to sign-off on.
“The first one is a road use agreement. In a nutshell it basically incorporates the developers promise to maintain and repair the roads if they are damaged during construction.” Ellis told the board. “They will be using some heavy equipment, trucks, trailers, you name it.”
Ellis added a pre-construction road survey will be done to determine the current road condition of Houghton Hill Road. He says both the solar developer and town will agree on what the current condition of the road is and then come to an agreement on what the bond agreement will be as they will bond the amount needed if damage occurs for financial security.
Speaking on the stormwater management plan, Ellis says the developer will have to install several different means of erosion control and stormwater control. He says this covenant is also there to maintain this agreement for the life of the project and will be enforced to the next owner if the project is ever sold off.
“This agreement gets recorded with the County Clerk and it runs with the land.” Ellis said. “So any subsequent purchaser of the property would be on notice and they would be responsible for maintaining those stormwater systems as well.”
Ellis said he has reviewed both agreements, along with the developer and their legal team to which all parties agree.

Town Councilmember Brandon Brown asked Ellis if the stormwater plan included through decommissioning to which Ellis confirmed. Councilmember Sarah Head asked the length of the road maintenance agreement, which would last only through the completion of construction of the project.
With no further discussion or questions, the town board unanimously passed both resolutions for the agreements.