Curb Work, Light Installation, and Sidewalk Forming Happening on Groton Ave.



As the end of the construction season looms, work on Groton Ave. continues with construction crews excavating for curb installation on a section of Homer Ave, Monroe Heights and Pleasant Street that lead to Groton Ave.

Crown City Rising reports work on the installation of a carrier pipe for Verizon is also being done on the street between Homer Ave. and Main Street with progress on lighting installation in the same section.

Additionally, sidewalk forming and concrete placing is being done with weather permitting between Homer Ave. and Main Street. The latest updates may be found at CrownCityRising.com.