Cortlandville Solar & BESS Committee Provide Presentation on Draft Laws



The Town of Cortlandville’s Solar & Battery Energy Storage System (BESS) Committee presented two draft local laws Wednesday night that would regulate future solar energy and battery storage projects within the town.

Committee member Glenn Reisweber, who led the presentation, emphasized that the meeting was intended solely to review the proposed laws and that no action would be taken. Later in the evening, the Town Board voted to table consideration of both laws until its June 17 meeting.

Reisweber said work on updating the town’s solar regulations and creating a new BESS law began more than two years ago after residents raised concerns about the impacts of nearby solar developments.

A task force formed in November 2024 gathered public input, visited properties affected by recent solar projects, and worked with the Cortland County Planning Board to study potential impacts and solutions.

As solar project applications continued to increase, the town enacted a six-month solar moratorium on Oct. 1, 2025, to allow time to review existing regulations and draft new legislation. A separate moratorium on battery energy storage systems followed in November 2025.

The town last updated its solar regulations in 2022.

“In December (2025) we started working groups,” Reisweber said. “We broke down into five groups and I asked each member of the team to become near experts. Learn as much as you can.”

Drafting work continued through January and February, followed by reviews from legal counsel, the Cortland County Planning Board, and the Town Planning Board. Public hearings were also held before the drafts were finalized.

“We wanted to make sure that [both draft laws] were tight on the legal front,” Reisweber said.

Committee member and Town Planning Board Vice Chair Ken MacDonnell outlined the proposed battery energy storage system regulations.

He explained that while battery storage technology is commonly found in cell phones, electric vehicles, and residential backup systems, the proposed law focuses on large-scale commercial facilities used to store electricity for the power grid.

“As New York State moves toward reducing dependence on fossil fuels, BESS will play an increasingly critical role,” MacDonnell said.

The draft law establishes a tiered permitting system:

Tier 1 (80 kW or less): Basic permits required, generally residential systems.
Tier 2 (80 kW to 600 kW): Requires a conditional permit, Planning Board review, public hearing, and notification of property owners within 500 feet.
Tier 3 (over 600 kW): Generally prohibited throughout the town except under limited circumstances.

The proposal would prohibit all BESS facilities in flood hazard areas. Larger systems would also be banned on Mineral Soil Groups (MSG) 1 through 4 and on prime agricultural soils.

Cortlandville Fire Chief Mike Biviano addressed one of the most frequently cited public concerns: fire safety.

Biviano said large lithium-ion battery systems can experience thermal runaway events that cannot be extinguished with water or foam and must be allowed to burn out. During such incidents, hazardous gases, including hydrogen fluoride, can be released, requiring specialized hazmat response and air monitoring.

MacDonnell noted that newer battery technologies designed to reduce fire risks are currently under development and could lead to future updates to the law.

The proposed BESS regulations would require:

  • Independent code-compliance reviews by a New York State licensed engineer.
  • Automatic fire detection monitoring connected to a 24/7 operations center.
  • Emergency response plans.
  • Thermal runaway detection systems.

All BESS facilities would be required to maintain a minimum 1,000-foot setback from homes, have a maximum height of 15 feet, and place utilities underground where feasible.

The committee also presented proposed revisions to the town’s solar regulations.

Reisweber said stormwater management has been the most common complaint associated with existing solar projects. Of the town’s nine solar fields, three have reportedly generated stormwater concerns from neighboring property owners.

Under the draft law, developers would be required to prepare a Stormwater Pollution Prevention Plan (SWPPP) and coordinate closely with the Cortland County Soil and Water Conservation District. Reviews would be funded through developer-backed escrow accounts.

The proposal would also restrict solar development on steep slopes. Solar panels would be prohibited on slopes exceeding 15%, while no more than 20% of a project’s total area could include slopes between 8% and 15%.

New noise standards would limit solar facilities to 45 decibels, roughly equivalent to rustling leaves or soft background music.

Committee member Bernice Potter-Masler, a third-generation farmer and vice chair of the Town Zoning Board of Appeals, highlighted the committee’s focus on preserving agricultural land.

“Cortlandville’s a town of 30,000 acres,” Potter-Masler said. “Agriculture has been the backbone of the town’s economy, of the county’s economy for a long time.”

She noted that agricultural land in Cortlandville declined from approximately 60% of the town’s acreage in the 1960s to 36% by 2010.

“The task force is concerned about keeping agricultural lands for agricultural use,” she said.

The draft law would prohibit large solar developments on the state’s most productive agricultural soils, classified as Mineral Soil Groups 1 through 4. However, projects could include up to 10% of those soil types when they are intermixed with less productive soils.

The proposal follows recommendations contained in the town’s 2018 Agricultural and Farmland Protection Plan by prioritizing solar development on brownfields, landfills, and less productive farmland.

The draft regulations would require soil and water testing before construction, annually during operation, and throughout the decommissioning process.

Developers would also be required to conduct wildlife corridor impact assessments to evaluate potential effects on habitat connectivity and wildlife movement.

For larger solar projects, developers would be required to enter into Host Community Agreements and Payment In Lieu of Taxes (PILOT) agreements to help offset impacts on municipal services, transportation infrastructure, agriculture, and community character.

Before construction begins, developers would also need to complete baseline studies documenting existing soil conditions, water resources, drainage patterns, topography, agricultural productivity, and vegetation.

Annual groundwater and surface water testing would be required throughout the life of the project.

No building permits would be issued until a decommissioning agreement and financial security plan are approved to ensure the site can be restored to its pre-construction condition when the project reaches the end of its useful life, typically after 20 to 30 years.

The full text of both proposed laws is available at Cortlandville.gov and at the Raymond G. Thorpe Municipal Building, 3577 Terrace Road, Cortland, during regular business hours.