Cortlandville Approves Study Amid Projected Surge in Route 13 Sewer Flows
The Cortlandville Town Board unanimously approved a $58,350 contract with CHA Consulting for a Route 13 Sewer Capacity Project during its meeting Wednesday evening.
The study comes as the town prepares for a significant increase in wastewater flows associated with the expansion of Byrne Dairy, which has projected substantially higher sewer use in the coming years.
According to town documents, Byrne Dairy currently generates approximately 204,000 gallons per day (gpd) of wastewater. Near-term projections for around 2028 anticipate an additional 336,000 gpd, while long-term buildout projections for around 2035 estimate an increase of 876,000 gpd.
Town Attorney Fran Casullo said the project is necessary as development continues in the southern portion of the town and existing sewer infrastructure may not have enough capacity to handle future flows.
Casullo also emphasized the need to find ways to share the cost of infrastructure improvements with other agencies and entities that could benefit from the project.
“The town cannot continue to finance all of these expenditures,” Casullo said, adding that he has been in discussions with other agencies in the county about potentially securing reimbursement for some of the town’s costs.
Sewer flow monitoring conducted in 2024 recorded peak flows along Route 13 of approximately 700 gallons per minute, with average flows of about 400 gallons per minute. Based on GIS data, town documents indicate the existing sewer pipeline may not have sufficient capacity to accommodate Byrne Dairy’s projected long-term needs.
As part of the study, TECSmith, a subcontractor on the project, is expected to install five temporary flow meters along Route 13. The meters will remain in place for six weeks.
CHA will use the data collected during that period to model dry- and wet-weather flow scenarios and evaluate potential upgrades to the sewer system.
If the study confirms a capacity deficit, CHA will develop preliminary engineering solutions and cost estimates. Potential remedies include constructing a parallel gravity sewer line or installing a new wastewater pump station and force main along Route 13.
The project comes as municipal officials look ahead to major increases in industrial wastewater flows in the southern portion of the town, primarily associated with Byrne Dairy. Wastewater from the Route 13 sewer system flows north before entering the City of Cortland’s network for treatment.
The $58,350 project is divided into three phases: $22,600 for the core evaluation and technical memorandum; $15,950 for six weeks of field flow monitoring; and $19,800 for concept modeling and cost estimates for potential upgrades.
Casullo said the town will continue to pursue reimbursement opportunities as the project moves forward.
“My hope is that if we’re spending this money, we’re going to get some of it back,” he said. “I do have some expectation that we’re going to get it back.”
A draft technical memorandum outlining existing capacity, projected future constraints and recommended upgrade options is expected to be presented to Supervisor Gregory Leach and the Town Board approximately six weeks after the field monitoring is completed.