City Planning Commission Approves Extensions for Gillette Skirt Factory Housing Project, Two Others
It was overall a relatively light agenda for the City of Cortland Planning Commission during their April meeting Monday evening. A majority of the items for the commission were to grant planning permission extensions for a variety of projects, including for the Gillette Skirt Factory at 32 Miller Street.
Calabro Properties, the developer of the old Gillette Skirt Factory seeks a site plan approval extension. The site plan was originally approved for an extension through June 6. The former factory looks to be completely renovated and feature 27,000 square feet of residential space consisting of 22 units along with 2 commercial office spaces. Two nearby houses were demolished as part of the redevelopment of the property for construction of an L-shaped garage with up to 8 garage spaces.
Speaking on the property was Troy Beckwith of Calabro Properties. Beckwith informed the Commission that the project was delayed due to design and engineering issues, but both have now been resolved. He added work on clearing out the inside of the building has begun and he anticipates construction to begin this summer. Beckwith noted work will take about two years to complete.
The Commission had no issue granting another 1-year extension for the site plan approval, previously granting an extension this time last year.
Two other projects were also granted extensions of site plan approvals. However, the Commission noted that this would be the last time for both projects to be given an extension otherwise they will have to obtain both planning and zoning approvals once again. Those projects are: 16 Owego Street where a 2-unit residence is planned and on Commando Ave the construction of three residential, owner-occupied homes.
Captain Roy Everett of the City of Cortland Code Enforcement Division spoke on the project at 16 Owego Street. Residents will know the property as currently having a large hole and fencing surrounding it since the demolition of a vacant house a number of years ago. Everett said the city has given notice to the developer to have foundation work completed by the end of May otherwise the city will fill the hole themselves and bill the developer for the work. The extension was granted until November of this year.
On Commando Ave the extension was granted to July 2027. Everett did inform the Commission the developer has obtained financing for the project and previous stipulations from the original approval, which included the demolition of a building on East Ave, have been done. Construction is expected to begin shortly.