A digital rendering of an industrial facility shows large interconnected buildings with multiple rooftop units and exterior pipes. The image includes the X101 Always Classic logo in the bottom right corner.
Local News

Byrne Dairy’s $120 Million Phase 2 Expansion in Cortlandville Continues to Make Process in Planning Stages – 100 New Jobs to be Created; 75 Construction Jobs



Byrne’s full expansion plans of Phase 2, 3, and 4.

During Tuesday’s Cortlandville Planning Board meeting Byrne Dairy provided an update on their planning progress for their $120 million phase 2 expansion of Byrne Hollow Crossing. Jim Gosier, General Counsel for Byrne provided a detailed update on the company’s progress.

The phase 2 expansion is a 100,600 square foot expansion of the current facility with 9 new dock doors. It will also have an expanded receiving bay totaling 4,238 square feet. Work will require the town to abandon Osbeck Circle, which is the current entryway to the facility; Byrne will build a new access road off of Byrne Hollow Crossing.

Mr. Gosier added there will be upgrades to the electrical substation and feeds, new truck parking/staging/loading/unloading area totaling 127,500 square feet, and a new 175,000 gallon water tank (this tank will be available to Cortlandville Fire in the event of a catastrophic fire).

The construction of the expansion is expected to create 75 jobs with the new expansion adding 100 jobs to the facility. Byrne currently employs 105 workers at the Cortlandville plant. Gosier added Byrne still plans to have future expansions of the facility, phase 3 and 4, but their main focus now is on phase 2.

The planned expansion was previously submitted to the Cortland County Planning Board for their review and recommendations. Mr. Gosier says the county provided 12 recommendations overall. So far, 9 of the 12 recommendations are done. The remaining three recommendations are: lot consolidation, confirming sufficient water capacity, and compliance with SEQRA. Gosier says the lot consolidation is under way, but Byrne is waiting for the town to abandon Osbeck Circle. He added Byrne is actively working to confirm the anticipated water usage and believes there is sufficient water for the plant, capacity for said water going into the plant, and sewer capacity. Byrne has their own waste-water treatment plant on site prior to it being placed into the public sewer.

For the SEQRA process, it is still pending for Byrne. Mr. Gosier said for the SEQR, Byrne has provided all the necessary information with the exception of the confirmation of sufficient water supply for operations. The Town of Cortlandville itself is allowed by the Susquehanna River Basin Commission to draw 1.3 million gallons of water each day from the aquifer. Mr. Gosier noted there are discussions to see if the 1.3 million gallon cap could be lifted as he says with Byrne’s operations, the town may get close to the daily limit allowed by the commission. Exact water usage for Byrne was not available during the meeting as data is still being collected.

“The bulk of the water [Byrne] uses is to clean the machinery. Doesn’t go into the product. There’s some that goes into the sanitary sewers, but the bulk of the water we use is to clean the machines.The less often you clean the machines, the less water you use. The state has blessed the operation because of the quality of our machinery and quality of our products. Has allowed us to go 72 hours without cleaning.” Gosier said to the Planning Board.

Byrne has obtained from New York State an Extended Run Authority. This allowance allows Byrne to clean machinery every 72 hours instead of every 24 hours. This allows a major reduction in water usage by allowing Byrne to use only ⅓ of the water it originally used for cleaning.

The Town of Cortlandville will also be constructing a new well. Byrne Dairy will donate a parcel of land for the construction of the well. The company had also paid for the well testing with results showing that the new well won’t affect other wells in the area. Town Attorney Fran Casullo says an agreement on the new well with the Town and Byrne could come as early as this week for the site of the new well. The town has applied for a $1 million dollar grant through the Empire State Development County Infrastructure Grant Program to help pay for the new well. A new well could cost between $3 and $5 million dollars, according to Town Board Member Guido during a previous meeting.