Four more streets have been added to the City of Cortland’s DPWs resurfacing project this construction season after announcing they were ahead of schedule.
The four streets in added to the list are:
- West Main St.
- Cowance St.
- Rob Roy St.
- Jewett Ave.
DPW crews will begin today, September 12th with West Main St. The milling process will take about 3 days for all four streets.
Once milling is completed, crews will then work on repairs to sanitary and storm sewer systems.
Paving will be expected to take place the last week in September based on weather conditions.