A Long Time Coming: Homer Prepares to Break Ground on Major Water Infrastructure Improvements
On the latest edition of Happenin’ in Homer, X101’s Matt Brooks chats with Village Clerk Dan Egnor about a long-overdue plan to replace two 100-year-old water tanks with a modern concrete version.
Click here for audio transcript. Audio transcription is edited for content.
Matt Brooks: Good morning, I’m Matt Brooks on X101, Always Classic, in for another edition of “Happening in Homer,” and—well, it’s been a minute—but Dan Egnor, Village Clerk at the Village of Homer, is back in the studio with me. How’s it going, Dan?
Dan Egnor: All right, Matt, how are you doing?
Matt Brooks: Oh, I’m doing fantastic. And what—we’ve got some pretty good news coming down the pipeline. Talk to me about some water tanks.
Dan Egnor: Well, the village has for some time been wanting to replace the two water tanks that, I believe, it’s called Caraway Hill over on the east side of the village. The pipes actually go under Interstate 81 and they’re over a hundred years old, I think. So, they’re—one is completely non-functioning, the other one is barely on life support. So, we’ve been working with our engineers from Barton & Loguidice to get a new water tank—or basically for redundancy—up right next to the water tank that already exists up above the cemetery. So we’re going to build it right to the west of that tank.
Matt Brooks: No, that sounds like a better idea as opposed to the amount of work involved to try to replace those tanks across 81. I’m sure we don’t need any more construction near 81.
Dan Egnor: Exactly. No more near construction, and then, you know, old pipes underneath a federal highway, they don’t like you doing any work around their highway. So, it’s a better fit to have it up on the—up on the hill over in the cemetery.
Matt Brooks: And this does sound like a pricey project—I mean, talking about millions of dollars. And that does raise some concern because the money’s got to come from somewhere. So, can you tell me about some of the backstory of how this project has really got to move on?
Dan Egnor: Certainly. We have a loan through EFC, that’s Environmental Facilities Corporation, for about $4 million. And also, though, we have a grant through the same entity for about $2.25 million. The overall project cost that’s being put together is around—let me check some notes—$3.5 million is what they have. And there’s a lot of costs in there, one of which is $700,000 in contingencies as well. What’s great about EFC—certainly with that $4 million—as the project commences, which we’re not going to commence until next year—that’s when the construction will start on the new tank—as costs come into the village, then we can package that, send it to EFC, they will send us back the money that we’re requesting, then we can send that out to the vendors and the contractors. As opposed to us doing the entire project, getting a $4 million loan or a bond, and then doing it and then asking, “Hey, can you give us money back?” like most grants are reimbursement. This one is where a pass-through. So, it’s beneficial to the taxpayers and it’s a great way of doing this project as it moves along.
Matt Brooks: Yeah, the way you’re describing it just—parting the pun—but the funds will be a lot more fluid.
Dan Egnor: Boom-boom. It’s true.
Matt Brooks: So, it’ll get to where they need to go. So, you mentioned construction not going to start till next year. Is there anything—I mean, to get the ducks in a row or anything to expect as we head towards that construction date?
Dan Egnor: Well, we just did—we did opening bids for the construction of the tank. Two groups applied. A group called Preload LLC was the winning bid. Their cost is around $2.5 million that they say they could do the project. And they’re just—this is all they do. They do these water tank projects, that’s the bulk of their business. And so they just have a bunch of projects all through the year, so they can’t get started till spring, early summer next year.
Matt Brooks: Well, it—I mean, we still got quite a bit of time, but if people want to learn more about the water tanks or many of the other projects that are quite literally in the pipeline, Dan, how do they keep up to date on what’s going on in the Village of Homer?
Dan Egnor: Certainly they could reach out to me, but every meeting we do grants updates, usually at least once or twice a month, so we talk about current projects and the status of those projects. So, that’s always going to be in there. There’ll be—and with those meetings there’ll be minutes afterward, so they can check the minutes up on the website. But if they want to go to the source, they could just email me or call me, just ask for Dan and I’ll let them know whatever they need to hear.
Matt Brooks: Well, it is exciting to hear that there’s really getting a move on this project and—I mean, it sounds like a long time, a year, but considering how some—long sometimes things move—
Dan Egnor: This project, yeah, this project has been in the idea mode since I got here, and that’s 2017. So, that’s how long it takes to get to where we’re at.
Matt Brooks: Wow. And I’m glad that we are—we’re going to be breaking ground soon. I’ve got to thank you, Dan, for stopping by, filling us in on what’s going on in Homer. And I can’t wait for the next time you stop in to talk about some of the projects going on.
Dan Egnor: As always, appreciate your time, Matt. Thanks.
Matt Brooks: It’s been another edition of “Happening in Homer” here on X101. I’m Matt Brooks.